HomeNewsUS$ 27bn investment required to mobilize global offshore wind supply chain

US$ 27bn investment required to mobilize global offshore wind supply chain

  • Investment required by 2026 if sector is to meet forecasted 5-fold growth in annual installations by 2030, with greater sum of US$100 billion needed to hit global government targets by the end of the decade.

The global offshore wind supply chain will require US$ 27 billion of secured investment by 2026 if it is to meet a fivefold growth in annual installations (excluding China) by 2030. This was according to latest Horizons report by Wood Mackenzie, a global insight business for renewables, energy and natural resources.

“Governments have made clear their commitment to offshore wind as an important pillar of decarbonisation and energy security. However, the supply chain is struggling to scale up and will be an impediment to achieving decarbonisation targets if change does not happen”, says Chris Seiple, Vice Chair, Power and Renewables at Wood Mackenzie, and co-author of the report.

Seiple added: “Nearly 80 GW of annual installations to meet all government targets is not realistic, even achieving our forecasted 30 GW in additions will prove unrealistic if there isn’t immediate investment in the supply chain. Adjustments and new policies by governments and developers will be required to transform the supply chain to deliver offshore wind projects at industrial scale.”

With low offshore margins which have made investment case more challenging and extremely difficult, Seiple also believes that the oversupply that resulted from the 2015 supply chain buildout has huge and tremendously negative impact on profitability.

He said: “The oversupply that resulted from the 2015 supply chain buildout is one of the factors depressing profitability, which saw the industry boost its capacity to supply around 800 turbines, compared to the yearly average of 500 since then. Suppliers are now also having to cope with the inflation of the past two years and higher commodity input costs.”

He added: “Burned once, current suppliers are cautious in their investment plans and the lack of profitability is hampering their ability to fund manufacturing capacity expansion – ultimately stalling innovation in the sector.”

On the uncertainty of project timing which could also result in very different supply-chain needs, the report showed that about 24 GW of projects which are scheduled to come online between 2025 and 2027 have already secured a route to market, through either some form of subsidy or power purchase agreement (PPA), even though a financial investment decision (FID) has not been made. And according to the report, the very critical stage is now, when developers look to firm up project orders with the suppliers, however with multiple global projects delayed, prompting renegotiations on offtake contracts, given increased supply costs and inflation.

With the shift in the anticipated equipment demand from 2025-27 toually2028-30, which also and naturally will result in less need for manufacturing expansion in the shorter term, there would be an even greater need for investment to expand to meet the demand from 2028-30.

Finlay Clark, Senior Research Analyst at Woods, and co-author, said: “In reality, if this occurs, certain projects might not get built at all in 2028-30, meaning governments will risk falling further behind their targets. The uncertainty surrounding project timing is a large reason why supply chain participants hesitate to expand further.”

This figure is based on Wood’s base case outlook which forecasts annual capacity additions to hit 30 gigawatts (GW) by 2030, to be dwarfed however by policymakers’ offshore wind targets, which would require nearly 80 GW per year. To hit this goal set by governments across the world says Woods, the supply chain is estimated to require more than US$100 billion in investment, findings which came from its “Cross currents: Charting a sustainable course for offshore wind.”

According to the report, many investors would be concerned that if the supply chain were built out to satisfy peak installation demand in 2030, in order to meet government wind targets, there could be insufficient demand for equipment to support it after 2030.

“This seems eerily similar to the post-2015 drop in margins across the supply chain. This is an important consideration for suppliers, in particular, as they need to be confident in the demand 10-plus years ahead to earn a return on their investment,” Clark added.  

Wood’s believe in scaling up therefore, the offshore wind supply chain will require a number of adjustments by governments and developers. It includes, first and foremost, target setting and plans for power market infrastructure to support offshore wind need extending beyond 2030, especially in places where they do not already do so. Policymakers to consider the impact on the supply chain when deciding whether or not to renegotiate existing contracts and pausing the turbine size arms race with a size cap.

Finally, Soeren Lassen, Head of Offshore Wind and co-author as well also noted: “It’s not all up to governments. Developers also need to consider innovative partnerships with suppliers to provide the demand stability that suppliers need to increase capacity.”

Seiple concluded: “The sector – most notably the policymakers – must take this opportunity to chart a more sustainable path for offshore wind. This will not just influence the projects being installed today or in 2030, but also the 1.4 terawatt (TW) offshore wind capacity that Wood Mackenzie expects to be connected by 2050.”